I have received some crazy quotes for a system at my house. One was 10KW (sunrun) for $45k and the other was for 12KW for $42k(400W Panasonic panels, enphase micro inverters). I want to get the NEM 2.0 agreement and install myself (with help). I have an EV as well as 3 heat pumps + a pool heat pump all being installed this year so I will not really know my power needs exactly. I have been running avg 37KW per day according to my bill so a 10KW system or greater is best. PVWATT says a 12KW system will produce ~20,000KWH a year at my location. My roof has good southern exposure with room for a 10KW system and a huge amount of west facing area for spillover. Couple of questions:
1. I am planning on using Enphase Energy IQ8 IQ8M-72-2-US micro inverters. But since I have no shade problems (except for marine layer!) should I use these?
2. The application to SDGE requires a specific panel model number and I need to submit this application ASAP. I have narrowed the panels down to Q.PEAK DUO BLK ML-G10+ 400 and Panasonic EVPV400HK. Are these good choices? Any other panels that would be better?
3. Although not necessary, I would like to have an AC disconnect switch. Will a 60amp switch work for a 12KW setup? Would a Siemens HNF362PV 60 A, 600V AC/DC, 3 pole, NEMA 1 be a good choice?
I am looking forward to this project and can def spend the money saved on install elsewhere. Any help appreciated.
Thanks for reading
1. I am planning on using Enphase Energy IQ8 IQ8M-72-2-US micro inverters. But since I have no shade problems (except for marine layer!) should I use these?
2. The application to SDGE requires a specific panel model number and I need to submit this application ASAP. I have narrowed the panels down to Q.PEAK DUO BLK ML-G10+ 400 and Panasonic EVPV400HK. Are these good choices? Any other panels that would be better?
3. Although not necessary, I would like to have an AC disconnect switch. Will a 60amp switch work for a 12KW setup? Would a Siemens HNF362PV 60 A, 600V AC/DC, 3 pole, NEMA 1 be a good choice?
I am looking forward to this project and can def spend the money saved on install elsewhere. Any help appreciated.
Thanks for reading