In about a month, I'm having a 10.075kW PV system installed with a StorEdge Inverter and LG Chem battery. For the Massachusetts SMART program, National Grid requires a dedicated meter to be installed between the inverter and your distribution panel to measure your PV generation so they can calculate how much to pay you.
The problem I see is the ESS and how the StorEdge Inverter is wired. Basically, the SMART meter will not measure the full PV generation when there is power draw from the backup loads panel. Please take a look at the attached diagram and let me know if I'm missing something or if there really is a potential problem.
- Soby
The problem I see is the ESS and how the StorEdge Inverter is wired. Basically, the SMART meter will not measure the full PV generation when there is power draw from the backup loads panel. Please take a look at the attached diagram and let me know if I'm missing something or if there really is a potential problem.
- Soby