In another post - I indicated that I received several quotes on a 18,500 kWh system, which is 120% of my annual electrical usage
I narrowed it down to two companies and the company that I chose was going to use (36) 320w LG panels. My 2nd choice was going to use (39) of the same panels to get to 18,500 kWh and they were quick to point out that the first company may be underbidding to get the contract and then perhaps try to increase the price later after the site survey....
My thoughts at the time were 'I have a production guarantee for 10 years, so why does it matter how many panels are installed'
However, at the insistence of my 2nd choice company, I looked at the fine print of their 10 year production guarantee, and it appears to me that unfortunately, it is not the worth the paper it is printed on
So it looks to me that they do not have to do anything unless the system produces less than 15,725 kWh annually and only then to they have to bring it up to 16,650 kWh to be in compliance - which is still far short of 18,500 kWh
Doesn't sound like much of a guarantee - or am I reading it wrong?
I narrowed it down to two companies and the company that I chose was going to use (36) 320w LG panels. My 2nd choice was going to use (39) of the same panels to get to 18,500 kWh and they were quick to point out that the first company may be underbidding to get the contract and then perhaps try to increase the price later after the site survey....
My thoughts at the time were 'I have a production guarantee for 10 years, so why does it matter how many panels are installed'
However, at the insistence of my 2nd choice company, I looked at the fine print of their 10 year production guarantee, and it appears to me that unfortunately, it is not the worth the paper it is printed on

During the first ten (10) years after installation completion, if, for any twelve (12) month period during the Guarantee Period (as defined below), the actual PV System output, as measured in kWh by customer's monitoring system ("Actual System Output) is more than fifteen percent (15%) below the projected total in kWh (as per this addendum) of the Estimated System Output for the same twelve (12) month period. XXXXX shall be obligated to cure any shortfall such that Actual System Output is within ten percent (10%) of Estimated System Output going forward.
Doesn't sound like much of a guarantee - or am I reading it wrong?