I noticed when looking at PG&E NEM tracking page that there's a second table (not sure if it's new or if I never noticed it before). It lists:
"Total NEW Requests Pending as of 4/24" as 432.15 MW.
This is described as "Total Submitted requests pending customer action such as providing final building permit to PG&E",
"Remaining MWs to NEM Cap Assuming All Pending Requests on the Line Immediately Complete their Projects...." 0.0 MW.
I thought people couldn't submit until they had been inspected already? Anyone have insight as to the significance of this number? There can't possibly be 432 MW coming online in the next 1-2 months? As of 4/24, the tracking page says 396.04 MW remaining to cap (NEM CAP minus (Cumulative MW installed under NEM + NEW MW In Queue)).
I'm hoping to get in under NEM 1.0 and have reroofing schedule for late June. Under my previous understanding understanding of the installation trends, there's been about 50 MW/month of installations, leaving about 8 months remaining (for 396 MW remaining), or if one were to assume an increase to an average of 80 MW/m, then ~5 months (September).
Under those estimates, it seems like I should be pretty safe installing in late June and turning on in early July. Am I missing something? The only other date that's relevant is the July 1, 2017 deadline, correct? Any thoughts on whether I should be safe to go ahead and sign a contract with a solar installer on this schedule?
NEM 2.0 doesn't look too bad, but I'm concerned that there's more things they can tweak in it which could lead exposure down the line, especially with the forced TOU. Under NEM 1.0 it's nice to know that I can at least switch to non-TOU, should they screw with the TOU schedules too much.
Thanks!
"Total NEW Requests Pending as of 4/24" as 432.15 MW.
This is described as "Total Submitted requests pending customer action such as providing final building permit to PG&E",
"Remaining MWs to NEM Cap Assuming All Pending Requests on the Line Immediately Complete their Projects...." 0.0 MW.
I thought people couldn't submit until they had been inspected already? Anyone have insight as to the significance of this number? There can't possibly be 432 MW coming online in the next 1-2 months? As of 4/24, the tracking page says 396.04 MW remaining to cap (NEM CAP minus (Cumulative MW installed under NEM + NEW MW In Queue)).
I'm hoping to get in under NEM 1.0 and have reroofing schedule for late June. Under my previous understanding understanding of the installation trends, there's been about 50 MW/month of installations, leaving about 8 months remaining (for 396 MW remaining), or if one were to assume an increase to an average of 80 MW/m, then ~5 months (September).
Under those estimates, it seems like I should be pretty safe installing in late June and turning on in early July. Am I missing something? The only other date that's relevant is the July 1, 2017 deadline, correct? Any thoughts on whether I should be safe to go ahead and sign a contract with a solar installer on this schedule?
NEM 2.0 doesn't look too bad, but I'm concerned that there's more things they can tweak in it which could lead exposure down the line, especially with the forced TOU. Under NEM 1.0 it's nice to know that I can at least switch to non-TOU, should they screw with the TOU schedules too much.
Thanks!
Comment