My PV ground mount is almost complete. All panels are in place and the wire pulled. However, there are a few things I don't like about the installation so far; am I being too picky?
Zip Ties: They use zip ties as cable clips. They say they are "UV resistant". I notice that the Ironridge website sells them as well. Is this acceptable? It may take a few years, but won't I eventually face a lot of sagging cables?
20150408_185406.jpg20150408_185457.jpg
Unfinished Frame Ends. The IronRidge frame sits on aluminium pipe. Shouldn't this be capped off to prevent critters and junk from filling it?
Pipe End.jpg
Crooked Inverter. This inverter was straight yesterday before the conduit was attached. I know the orientation doesn't affect anything, but shouldn't it be straight?
20150408_185752.jpg
Zip Ties: They use zip ties as cable clips. They say they are "UV resistant". I notice that the Ironridge website sells them as well. Is this acceptable? It may take a few years, but won't I eventually face a lot of sagging cables?
20150408_185406.jpg20150408_185457.jpg
Unfinished Frame Ends. The IronRidge frame sits on aluminium pipe. Shouldn't this be capped off to prevent critters and junk from filling it?
Pipe End.jpg
Crooked Inverter. This inverter was straight yesterday before the conduit was attached. I know the orientation doesn't affect anything, but shouldn't it be straight?
20150408_185752.jpg
Comment