What's frustrating is how did this guy not even think to ask what is required for a permit revision? After the inspection failed and I called the city to see what would be needed to file a revision, they gave me a list of items:
1. Letter of changes
2. Two copies of revised permit
3. $150 fee
4. 5 day review period
Did he not even think to ask? I swear it seems like he is dragging this out on purpose, I can't think of any other reason why it's been such a long process.