PNM says either upgrade the transformer or downsize my expansion proposal.
Collapse
X
-
-
my electric co-op made me add batteries and solar to the back feed request (56x295+8x5000=56,520w or 235 amps). they had me sign a agreement that i will not backfeed more then 200 amps, reasonable!Comment
-
No, they made me add my battery inverter output to my solar as total exportable energy. They are anticipating a distributed grid program.Comment
-
It sure seems to me that utilities, at least PNM anyways, is in no great big hurry for solar projects. My transformer upgrade request was given to a PNM engineer on March 1, according to the PNM e-mail they sent me. I e-mailed him last week about where we were on this. Today he responded and said sorry for the wait, and looked up my project and this is your "ballpark" cost. If I want to proceed, then let him know, and he'll start the process, and get me a in stone quote. Hmmm...I thought that's what I've been waiting on for the last 3 1/2 weeks. I guess maybe he thinks the "ballpark" price may scare some off, and then they won't have to do the engineering work on it. I get that I guess. The ballpark was $2500, and he said the actual cost is usually, (but not always) less than that.Comment
-
Dave W. Gilbert AZ
6.63kW grid-tie ownerComment
-
since you are pay for the transformer upgrade, ask how many tesla powerwalls you can add with new transformer? and beat your neighbor to that capacity. my power company treats batteries the same as solar and i had to add them to my backfeed request, puts me over 50kva. my transformer is 100kva and feeds 4 houses with 320 amp service, so i don't know how that all works. 100kva divided by four is 25kva, which is 104 amps per house.... anyway, next person will probably have to pay for a transformer upgrade... poor bast@rd...Comment
-
since you are pay for the transformer upgrade, ask how many tesla powerwalls you can add with new transformer? and beat your neighbor to that capacity. my power company treats batteries the same as solar and i had to add them to my backfeed request, puts me over 50kva. my transformer is 100kva and feeds 4 houses with 320 amp service, so i don't know how that all works. 100kva divided by four is 25kva, which is 104 amps per house.... anyway, next person will probably have to pay for a transformer upgrade... poor bast@rd...Comment
-
The way it was explained to me, is at least here in New Mexico, is PNM is required to provide 15% of their power from RE sources. With us installing our solar systems, we are saving PNM from having to pay for that infrastructure themselves. They get credit for every system put in, towards that 15% requirement. I don't know for sure, but I suspect they've met that requirement, as reflected in the dismal REC's they now pay. Plus, at least in my case, they seem to be slow walking my project. When the engineer finally gets me a in stone quote, then they'll have to wait for the check to clear, then I get put on a list for the upgrade. Who know's how long all that's going to take. NM only has so much money for the 10% tax credit they offer. If that gets used up, there's no more unless our politicians do something. That tax credit went away for 5 or 6 years, and only last year was implemented again when we got a new governor. I'd hate for this to drag on and the fund runs dry for my project.Comment
-
NMDan,
I reside in NM and am in the process of installing a 12.96kw system. I was initially told, by PNM, that the transformer in my area would support 5.5kw. I already had the equipment and was hell bent on getting the whole enchilada on the roof. I requested the transformer upgrade. To my surprise, the upgrade was done at their expense(I fully expected to pick up the cost). I was informed, by two of my neighbors, that the install would take place on a given date. A PNM contracted crew showed up and upsized the transformer. I talked to my contact at PNM and was told that on rare occasions they pick up the install. The PNM approval took 3 months and 3 plan changes. I got the approval to install and am in the process of lining up an electrician to complete the install and grid tie. I wanted to do DIY as much as possible. I am at the point that the permitting is going to require a licensed electrician.
On another front: two of my neighbors have solar installed. One of them added to their system to aid in the charging of a couple of electric cars. They had to pick up the expense of the the transformer upgrade. I guess I got lucky.Comment
-
NMDan,
I reside in NM and am in the process of installing a 12.96kw system. I was initially told, by PNM, that the transformer in my area would support 5.5kw. I already had the equipment and was hell bent on getting the whole enchilada on the roof. I requested the transformer upgrade. To my surprise, the upgrade was done at their expense(I fully expected to pick up the cost). I was informed, by two of my neighbors, that the install would take place on a given date. A PNM contracted crew showed up and upsized the transformer. I talked to my contact at PNM and was told that on rare occasions they pick up the install. The PNM approval took 3 months and 3 plan changes. I got the approval to install and am in the process of lining up an electrician to complete the install and grid tie. I wanted to do DIY as much as possible. I am at the point that the permitting is going to require a licensed electrician.
On another front: two of my neighbors have solar installed. One of them added to their system to aid in the charging of a couple of electric cars. They had to pick up the expense of the the transformer upgrade. I guess I got lucky.Comment
-
Our service is underground. It took about two hours for the ground based transformer to be swapped out. I would assume that a pole mount should be about the same.
There was recently a story on the news about issues people in the Northeast heights were facing in getting PNM approval for a system. It turns out that their equipment, that is beyond the transformer, needed to be upgraded. The expense to PNM is in the millions. They weren't as pro-active in getting that upgrade completed.Comment
-
My street is horseshoe shaped and has about 20 homes. Seven of us have solar power. I've wondered about all the excess voltage sent to the lines and how they handle it all. My neighbor across from me has at least a 10KW system and we share a transformer. Next door neighbors both have large systems and they also share a transformer.Comment
-
9 kW solar, 42kWh LFP storage. EV owner since 2012Comment
-
Finally some progress folks. PNM was out first thing this morning and it took them 90 minutes to replace the transformer. The cost to me was $1618.34 after the $900 credit for the old transformer. 20210519_091046_resized.jpgComment
-
Comment
Comment