Hello all,
I am new on here and sorry for the lengthy message below, but I am desperate for advice as in a battle with eON over sizing.
Not only did they install less panels than would fit on my roof, after telling me that 10 panels either side was the maximum, they also fitted a very small (in my opinion) inverter.
I have a E/W configuration with 10 panels each side and Trina 325w panels. This gives a total of 6.5kW, although I am aware that due to the orientation they will not give 100%. I am finding however that the 4kW Solis inverter is hitting its maximum if 4.34kW at about 10:20 and then still able to generate this at 15:20 in the afternoon and it is not even Summer yet.
I have graphs I can share and I have had loads of info form eON, stating that under specifying the inverter is common practice, but by 47% seems excessive. I asked for a 4.6kW inverter at the install time, which could peak to 5kW, but I was told due to the configuration I would never generate this.
Does anyone know for the G99 application whether the reason for the 4kW rather than 4.6kW was a pricing issue with the distribution company. If I has been able to choose, I would have had the extra 4 panels (12 each side) and a 5kW hybrid inverter so I could have added the battery later.
Many thanks for your replies
Clipping.png
I am new on here and sorry for the lengthy message below, but I am desperate for advice as in a battle with eON over sizing.
Not only did they install less panels than would fit on my roof, after telling me that 10 panels either side was the maximum, they also fitted a very small (in my opinion) inverter.
I have a E/W configuration with 10 panels each side and Trina 325w panels. This gives a total of 6.5kW, although I am aware that due to the orientation they will not give 100%. I am finding however that the 4kW Solis inverter is hitting its maximum if 4.34kW at about 10:20 and then still able to generate this at 15:20 in the afternoon and it is not even Summer yet.
I have graphs I can share and I have had loads of info form eON, stating that under specifying the inverter is common practice, but by 47% seems excessive. I asked for a 4.6kW inverter at the install time, which could peak to 5kW, but I was told due to the configuration I would never generate this.
Does anyone know for the G99 application whether the reason for the 4kW rather than 4.6kW was a pricing issue with the distribution company. If I has been able to choose, I would have had the extra 4 panels (12 each side) and a 5kW hybrid inverter so I could have added the battery later.
Many thanks for your replies

Clipping.png
Comment