I am planning on installing a small solar panel array (4-6 250 watt panels) outside on the ground most likely using a ballast ground mount system (like ecofoot2). I plan on using USE or UF cable running from panels to conduit going under ground (only distance of about 5 feet) from solar panel array and then coming up out of ground in pvc conduit next to side of house into an LB junction box and then small section of conduit through house wall to basement. I'd like to transition in the junction box outside from the USE or UF or THWN to romex and then romex through basement above drop ceiling (not in conduit) to the dc disconnect. The run in the basement will be about 35 feet. I'd like to avoid the hassle of running conduit in the basement if possible as I know thhn must be in conduit.
Questions:
Will this work?
Are there any issues doing this (breaking codes, etc)?
Is there a better way?
Questions:
Will this work?
Are there any issues doing this (breaking codes, etc)?
Is there a better way?