Hi All,
I have a question about what the best and most efficient way is to install PV Modules including the Sungrow Rapid Shutdown RSD device.
First install all RSD
Then install all PV Modules
Then do all connections and cable management
Or
Install the RSD and the PV Modules at the same time
Then make the connections and do cable management
Or
Install the RSD and the PV Modules at the same time and also make the connections and do cable management at the same time
Does anybody has experience with this? For us it is the first time
Kind regards and thx in advance
Ben
I have a question about what the best and most efficient way is to install PV Modules including the Sungrow Rapid Shutdown RSD device.
First install all RSD
Then install all PV Modules
Then do all connections and cable management
Or
Install the RSD and the PV Modules at the same time
Then make the connections and do cable management
Or
Install the RSD and the PV Modules at the same time and also make the connections and do cable management at the same time
Does anybody has experience with this? For us it is the first time
Kind regards and thx in advance
Ben