We're an installer in AR/OK working on a grid-tied job. We subcontract with a local licensed elec to do the bottom-side work. Work is similar to residential electrical work EXCEPT when we get to the line tap. That's always something new for them. We've never worked with this particular elec contractor before. At this job, the line side comes directly off meter into a 200A main breaker. There is a metal connector from the meter to this breaker. From load side of breaker, the wires leave this meter/brkr box and travel into the load center. I'm not sure if the LC has main breaker or not.
We've asked elec to line tap in the meter box downstream of the 200A breaker where there is room to do it. I'm getting pushback that we need to be on the line side of this breaker...but since it is a meter ring/breaker combo with a metal connector we can't attach on the top side. We're not in any electrical jurisdiction (no permit or inspection req'd), but when we install in places where we are inspected in AR, we've backfed through the main breaker. Case in point...the meter box on my house inside city limits of Little Rock where we did exactly that.
I understand the 120% rule as it applies to bus bars and breakers. Here we are backfeeding JUST through a 200A breaker. Googled it and everything found relates to 120% rule. Absent of any local jurisdiction rqmts, what is NEC say about backfeeding just through a breaker? We do it when we backfeed smaller systems directly into the load center. Why would this be any different...it's just a larger breaker.
Looking for some kind of guidance to get this elec off my back and just finish the job.
Sorry I would upload pics, but the upload attachments link here gives me an error.
We've asked elec to line tap in the meter box downstream of the 200A breaker where there is room to do it. I'm getting pushback that we need to be on the line side of this breaker...but since it is a meter ring/breaker combo with a metal connector we can't attach on the top side. We're not in any electrical jurisdiction (no permit or inspection req'd), but when we install in places where we are inspected in AR, we've backfed through the main breaker. Case in point...the meter box on my house inside city limits of Little Rock where we did exactly that.
I understand the 120% rule as it applies to bus bars and breakers. Here we are backfeeding JUST through a 200A breaker. Googled it and everything found relates to 120% rule. Absent of any local jurisdiction rqmts, what is NEC say about backfeeding just through a breaker? We do it when we backfeed smaller systems directly into the load center. Why would this be any different...it's just a larger breaker.
Looking for some kind of guidance to get this elec off my back and just finish the job.
Sorry I would upload pics, but the upload attachments link here gives me an error.
Comment