Am thinking of using solar power to run my room Air Conditioner during day time.
Have a 18000 BTU ( 1.5 tons ) split air-conditioner runs on 220V AC, 50Hz. At start it draws a 30Amps current for few milliseconds, and then it comes to 12 Amps for few seconds, and then after say 15 to 20 seconds its current requirement comes to 8 Amps.
My idea is to find some soft-starter or a VFD ( Variable Frequency Drive ) so that I am able to nullify the starting torque current of the air-conditioner. And after its installation, I hope then I just have to worry for 8 Amps regular current requirement only.
This 8 Amps of current needed makes power requirement of my A/C 1800 Watts.
If I install solar panels of 2500 Watts, and a MPPT charge controller , then I guess, that I be able to have sufficient power to run my A/C during day-time for 6 to 7 hours.
Now I come to question about battery costs. This cost is high, and I wish to by-pass this cost.
Upon installing a Soft-Starter / VFD to the air-conditioner. And having 2500 Watts panels, a MPPT controller, and an off-grid Inverter ( no batteries connected ). Would I be able to run the Air-Con during 5 to 6 hours a day ?
Please comment on the above.
Have a 18000 BTU ( 1.5 tons ) split air-conditioner runs on 220V AC, 50Hz. At start it draws a 30Amps current for few milliseconds, and then it comes to 12 Amps for few seconds, and then after say 15 to 20 seconds its current requirement comes to 8 Amps.
My idea is to find some soft-starter or a VFD ( Variable Frequency Drive ) so that I am able to nullify the starting torque current of the air-conditioner. And after its installation, I hope then I just have to worry for 8 Amps regular current requirement only.
This 8 Amps of current needed makes power requirement of my A/C 1800 Watts.
If I install solar panels of 2500 Watts, and a MPPT charge controller , then I guess, that I be able to have sufficient power to run my A/C during day-time for 6 to 7 hours.
Now I come to question about battery costs. This cost is high, and I wish to by-pass this cost.
Upon installing a Soft-Starter / VFD to the air-conditioner. And having 2500 Watts panels, a MPPT controller, and an off-grid Inverter ( no batteries connected ). Would I be able to run the Air-Con during 5 to 6 hours a day ?
Please comment on the above.
Comment